Past Transactions Summary
- In total 147 M W and 450 GWh/year production.
- Mersin WPP was developed at 2008 and Şah WPP at 2009.
- Mersin WPP was commissioned in March 2010 and Şah WPP in May 2011.
- Projects are among the best in the country interms of capacity factor.
- 21 MW and 70 GWh/year production.
- Seferihisar WPP was developed between 2012 and 2015.
- Seferihisar WPP was commissioned in June 2016.
- The project is located in Çeşme Region where is one of the most windy regions of the country.
- 77 M W and 270 GWh/year production.
- Edincik WPP was developed between 2009 and 2011.
- Edincik WPP was commissioned in July 2013 .
- This Project was also one of the best interms of capacity factor.
- 49 MW and 170 GWh/year production.
- Kartal WPP was developed between 2013 and 2018.
- Kartal WPP will be commissioned at the end of 2020.
- Kartal WPP is in a region where is one of the most preferred for WPP Projects in the country.